Home - Business Categories - Oil & Gas Field Facility
Oil & Gas Field Facility

CPP has a long history in oil and gas field surface facility construction. The business covers oilfield surface facility construction, civil work, storage and transportation, wellpads surface electrical work, all kinds of pipeline laying and various storage tanks installation. The company is capable of completing 1,000,000t/a product construction. Although the company has excellent performance in large-scale oil and gas gathering and transportation projects in China, it has also participated in the construction of oilfield surface facilities in Sudan, Algeria, Turkmenistan, Niger, Libya, Iraq and other countries. CPP has also built the first petroleum city of Niger in the Sahara Desert, with its high quality project, Niger Agadem oilfield surface facility(Phase 1) with the production capability of 100×104t/a.

zyyw_6_01.jpg

Niger Agadem Oilfield Surface Facility Construction

Customer: CNPC Niger Petroleum S.A.

Covered Area: Sahara desert hinterland in Niger

Scope of Work: 1 Union Station, 1 Oil and gas interchange Station, 5 metering station, 22 single wells and the main pipeline more than 200 kilometers.

Work Scope: construction

Annual Capacity: 1 million tons

Construction Time: 2009 -2011


zyyw_6_02.jpg

Changqing Oilfield Surface Facility Construction

Customer: PetroChina Changqing Oilfield Company

Covered Area: Neimenggu Erduosi, Shanxi Yan’an and Yulin, Gansu Qingyang, total area is about 20×104 km2.

Scope of Work: Build 26 new stations in 2014; rebuild47 existing stations; install 4108.67km pipeline included 2424.94km gas transporting pipeline, 1533.83km alcohol injection pipeline, and 149.9km water injection pipeline.

Scope of Work: construction

Construction Time: 2013 -2014


QQ图片20170417145243.jpg

Niger Petroleum Road Project

Customer: CNPC Niger Petroleum S.A.

Covered Area: start from Diffa Province in the south of the Niger, through N'Guigmi, to the frontier of Chad.

The total length of the main line is 181.6km and the length of municipal road is 14km. The design standard is Grade 3 and Asphalt concrete pavement. The cumulative equivalent axles during the design life span is 76×10times per lane.

Work Scope: Road construction

Construction Time: The first phase of the project was completed at the end of 2014.


4华北油田永清气站.jpg

Huabei Oilfield Surface Facility Construction

Customer: PetroChina Huabei Oilfield Company

Covered Area: Huabei and Inner Mongolia Erlian, total area is about 13×104 km2.

Scope of Work: Building 1 station; rebuild15 existing stations; install 178km pipeline including water injection pipeline and production pipeline.

Scope of Work: construction

Construction Time: 2014 -2016


5浙江油田地面建设.jpg

Zhejiang Hai Yi Combination Station Surface Facility Construction

Customer: PetroChina Zhejiang Oilfield Company

Scope of Work: Zhejiang Hai Yi Combination Station Surface Facility Construction. Install 23.27km water injection pipeline, 13.6km gathering and transportation pipeline. Build 1 pressure increasing treatment station, 3 heating treatment stations, 1 skid-mounted pressure increasing treatment station; install 15 sets of heater on the wellhead, 6 water injection valves, wellhead process installation of 34 oil well, process installation of 16 water injection wells, power and instrument, install19 well sites.

Scope of Work: construction

Construction Time: 2009 -2010


6华北油田樊庄煤层气产能建设.jpg

Huabei Oilfield Company Fanzhuang Coalbed Methane 57400×10m3/a Production Capability Construction Project

Customer: PetroChina Huabei Oilfield Company

Scope of Work: Construct 1 central processing plant, 6 gas gathering stations, install 5 gas gathering main pipelines, civil work, electrical and instrument, and auto-control etc.

Scope of Work: construction

Production Capability: 10 billion m3

Construction Time: 2008 -2009